Infrastructure packages in Saudi Arabia are paced by approvals as much as by site work. Every water, sewage, power and telecom network needs its design approved, its excavation licensed and its handover accepted before the municipality grants final approval. This guide maps those approvals and what your PMO should track.
A Saudi infrastructure package needs land scheme approvals from the municipality on Balady, design approvals from NWC, SEC and CST through MOMAH's Etmam developer services, and an excavation licence for each trench. Final approval is only granted after the infrastructure is handed over with completion certificates from the service authorities, so your project software must track every approval stage with dates, owners and days pending, not just physical progress.
On this page
- Why approvals, not concrete, set the pace of Saudi infrastructure
- The approval map: who signs off what
- The land scheme lifecycle on Balady
- NWC, SEC and CST: designs, works and handover
- Excavation licences and coordination through Balady
- Where infrastructure packages lose time
- What infrastructure project software should track
- A six step plan to get approvals under control
- How Shyphan's infrastructure PMO platform fits
- FAQ

Why approvals, not concrete, set the pace of Saudi infrastructure
On a typical serviced land package in Saudi Arabia, the civil work is rarely the hardest part. Crews can lay a storm line or pull MV cable in weeks. What takes longer is getting each design, each excavation and each finished network signed off by the right authority, in the right order.
A single package can involve the municipality or Amanah for the land scheme and roads, the National Water Company (NWC) for water and sewage, the Saudi Electricity Company (SEC) for the power network and the Communications, Space and Technology Commission (CST) rules for telecom infrastructure. Each has its own portal, documents and review cycle.
That is why infrastructure project management software in Saudi Arabia has to track approvals as closely as physical progress. If the PMO only measures metres of pipe, it will report a package as 90% complete while plots still cannot be released.
The approval map: who signs off what
The Ministry of Municipalities and Housing (MOMAH, earlier known as the Ministry of Municipal, Rural Affairs and Housing, or MOMRAH) runs two digital channels that matter here: Balady for municipal services and Etmam, its centre for real estate developer services. Etmam's service list includes water services, sewage services, approval of the infrastructure network design for SEC, and both infrastructure design approval and receipt of infrastructure by CST (Etmam services list).
| Authority | What it approves | Main channel | What your PMO should log |
|---|---|---|---|
| Municipality / Amanah | Preliminary, detailed and final land scheme approvals; road and public realm works | Balady | Decision numbers, service authority requirements, completion certificates |
| NWC | Water network and sewage network designs | Etmam | Design submission date, comments, resubmissions, approval letter |
| SEC | Electricity infrastructure network design | Etmam | Design version, approval reference, conditions |
| CST | Telecom infrastructure design and receipt of the built infrastructure | Etmam | Design approval, receipt approval, licensed provider involved |
| Municipal project coordination offices | Excavation licences inside city limits | Balady | Licence number, routes, start and end dates, clearance |
The exact documents and review times change, so check each service card before you plan a submission. The point for the PMO is simple: every row in this table is a separate clock that can stop work on site.
The land scheme lifecycle on Balady
For private land inside urban boundaries, Balady splits plan approval into three services. Their published requirements show how utility approvals feed the municipal process:
- Preliminary approval. Approves the subdivision plan. Listed requirements include a cadastral report, a valid electronic title deed, a contract with an engineering office, a conceptual design, a soil study and a hydrological study. The service card shows a 60 day service duration (Balady preliminary approval).
- Detailed land scheme approval. Holders of a preliminary approval decision obtain detailed approvals from the relevant service authorities. The requirements include the preliminary approved drawing, a conceptual design and the requirements from service authorities (Balady detailed approval).
- Final approval. Granted after the infrastructure is completed and handed over to the relevant service authorities. The requirements include the executed land scheme and completion certificates from those authorities, and the service supports the subdivision reports needed for title deeds (Balady final approval).
Read that last step carefully. Final approval depends on handover certificates from the utility authorities. A missing NWC, SEC or CST handover is not a utility problem only: it holds the whole scheme. Master developers planning phased releases should read our note on PMO software for infrastructure and master developers.
NWC, SEC and CST: designs, works and handover
Each utility runs its own review, but the pattern is similar: approve the design, supervise the works, then accept the finished network.
- NWC. Water and sewage design approvals for developers are listed as Etmam services. NWC is also named by MOMAH as one of the service entities that obtain excavation permits through Balady (MOMAH excavation permits).
- SEC. Etmam lists a dedicated service for approval of the infrastructure network design for the Saudi Electricity Company. SEC is also a service entity on the excavation permit service.
- CST. Telecom has two Etmam services: design approval and receipt of infrastructure. CST's regulations, first issued in 2018, set out the rights and obligations of property owners, developers and licensed providers for outside plant and in-building telecom infrastructure, and call for work in coordination with other public utility providers to reduce repeated digging (CST announcement). In August 2024 CST consulted on regulations for telecom services in real estate that list the responsibilities of land developers (CST consultation).
In practice, PMOs get better control when they break each authority into the same four stages: agreement or application, design approval, contractor or consultant approval, and handover. Each stage gets a submission date, an expected date and a named engineer. Contractors who build these networks for several clients can see how that looks in project tracking for utility network contractors.
Key takeaways
- Final land scheme approval on Balady requires completion certificates from the service authorities, so one missing utility handover holds the whole package.
- NWC water and sewage, SEC network design and CST design and receipt approvals are all listed as Etmam developer services.
- Excavation licences need registered contractors with valid City Service Provider Classification Certificates and are limited to 1,000 linear metres per excavation.
- MOMAH licence periods of 30 days on highways and 60 days on other roads make inspection delays a scheduling risk.
- Track every approval stage with a submission date, expected date, owner and days pending, alongside weighted physical progress.
- Check every service card before you plan, because documents and review times change.
Excavation licences and coordination through Balady
No trench opens inside city limits without an excavation licence. Balady's excavation services are built for utility entities such as telecom, electricity and water companies, whose representatives work through the Infrastructure Project Coordination Office in each municipality (Balady new excavation licence). The published conditions include:
- Contractors and consultants registered on the work team must have active commercial registrations and a valid City Service Provider Classification Certificate for the whole excavation period.
- Main contractors and subcontractors must be pre-qualified within the municipality's jurisdiction.
- Excavation routes are submitted as shape files, with a site safety plan and, where a road is closed, a traffic control plan.
- A single excavation is limited to 1,000 linear metres of routes and no more than 5 paths per work location.
For larger projects, the multiple excavations coordination service clears several excavations with all relevant entities at once. Balady is clear that the coordination report is not a permit: each excavation still needs its own previously coordinated excavation permit and fees (Balady multiple coordination).
MOMAH's excavation licence regulations, announced on 9 March 2024, set licence periods of 30 days for general excavation on highways and 60 days on other main, sub main and local roads, require supervision by an accredited consulting office, and require municipal fines to be settled within 60 days (MOMAH news). Short licence windows are a scheduling fact: if a trench waits for an inspection, the licence clock keeps running. Teams running roads and streetscape packages can compare notes in road and municipal works tracking.
Get your approvals under control
See how Shyphan's infrastructure PMO platform tracks NWC, SEC, CST and Amanah approvals alongside weighted site progress, in English and Arabic.
Where infrastructure packages lose time
Approval-heavy packages tend to lose time in a few repeat patterns, and none of them shows up on a bar chart:
- Silent waits. A design sits with an authority and nobody counts the days until it blocks a crew.
- Revision loops. Comments come back, the resubmission is sent by email, and the stage is never updated.
- Several Amanah departments. Roads, lighting, parks and floods teams review their own reports. One late reply can hold handover.
- Utility clashes. An existing duct or pipe on the alignment needs a diversion design before digging continues.
- Unweighted progress. Storm, MV, telecom and asphalt are reported in different units, so overall completion is a guess.
- Expiring credentials. A lapsed classification certificate or commercial registration stops a contractor from appearing on a licence request.
What infrastructure project software should track
Whatever system you choose, check that it can hold these records per package:
| Area | What good looks like |
|---|---|
| Authority approvals | Authority, stage, status, submission date, expected date, days pending, days late, reference number, responsible engineer |
| Ageing | Open stages grouped by age, most overdue first, with a portfolio view across authorities |
| Municipal submissions | Department, submission type, report number, review stage and revision history |
| Physical progress | Weighted milestones per trade, so site percentages roll up to one completion figure |
| Site updates | Previous and new percentage kept, with the constraint, next action and a photo |
| Documents | Drawings, approval letters and handover packages with numbers and versions |
| Issues and risks | Utility clashes, pending inspections and supply problems with an owner and target date |
| Reporting | Delay, overdue approval and health reports per director, exported for steering meetings |
| Language | Full Arabic interface with right-to-left layout and Arabic names for authorities and departments |
Consultancies reporting across many clients should also test portfolio views and director filters, as covered in portfolio reporting for PMO consultancies.
A six step plan to get approvals under control
- List every authority and stage. For each package, write down every NWC, SEC, CST and Amanah approval you need, from design to handover.
- Date every open submission. Record when it went in and when you expect a reply. Days pending only work if the start date is real.
- Name an owner. Every stage gets one responsible engineer, not a team inbox.
- Agree milestone weights. Fix the weight of each trade with the client before reporting, so completion figures are not argued in meetings.
- Check contractor credentials. Track classification certificates and commercial registration expiry for every contractor and consultant you will put on excavation requests.
- Review exceptions weekly. Overdue approvals, late milestones and packages near their due date go on one list for directors.
How Shyphan's infrastructure PMO platform fits
Shyphan's Infrastructure Project & Approval Management (PMO) software is built for this kind of package. It tracks thirteen weighted physical milestones per package, from backfilling and storm network to MV electricity, telecom, asphalt and road marking. NWC, SEC and CST approvals are tracked stage by stage with days pending, days late and ageing buckets, and Municipality submissions move through submitted, audit review, revised submission and final approval across sixteen Amanah departments. Site updates keep the old and new percentage, and twelve standard reports export to PDF or Excel, in English or Arabic.
Know its limits. It does not connect to Balady, Etmam or any authority portal, so submissions are logged by your team. Project health and the attention list are rule-based, not AI. It has no budgets, BOQs, invoices or payment certificates; for cost control, pair it with a construction and contracting ERP. Hijri date display is planned, not live.
A Saudi infrastructure contractor runs its PMO on this platform: see the contractor case study. You can open the live demo and pick a role on the sign-in screen, or request a quote and Shyphan will map your authorities and stages during implementation.
Sources
- Infrastructure Project & Approval Management (PMO) software
- PMO software for infrastructure and master developers
- Project tracking for utility network contractors
- Road and municipal works tracking
- Portfolio reporting for PMO consultancies
- Construction and contracting ERP
- Contracting management ERP
- All Shyphan products
Frequently Asked Questions
Which authorities approve infrastructure in a Saudi land development?
What is needed for final approval of a land scheme?
Who applies for excavation licences?
Is a multiple excavation coordination report a permit?
How long is an excavation licence valid?
Does Shyphan's PMO platform submit to Balady or Etmam?
Related reading
- Shyphan featured in Zoho Partner Times, Q3 2026
- Shyphan recognised as a Q3 2026 Top Zoho Partner in MEA
- How Shyphan became a Zoho Premium Partner in 8 months
- AI agent development
- AI development company in the UAE
- Zoho Premium Partner in the UAE
- Zoho Premium Partner in Saudi Arabia
- AI chatbot development cost in 2026
- 10 Zoho CRM implementation mistakes to avoid